Your build timeline.
What happens each week from signed contract to keys in hand, and the walk-throughs we'll do together along the way. The build clock starts when your septic or general building permit is issued; from there, a typical build takes about 22 weeks.
The weeks count from the day your septic or general building permit is issued, because how long permitting takes is up to the county. Some things are outside the builder's control. County permitting, inspection scheduling and the weather all set their own pace. Because of them, there can be unforeseen delays at any stage. When something changes, we'll tell you right away and update your timeline.
-
Before your permit
Contract signed
- Buyer and seller sign the New Construction Purchase & Sale Agreement
- Contract goes to the closing attorney
- Contract goes to the lender
- Builder finalizes the construction timeline
-
Before your permit · timing depends on the county
Preconstruction & permitting
- Lot survey and staking
- Permit package submitted and permitting underway
- Utility locates requested
- Selections sheet locked so long-lead items can be ordered
- HOA or ARC submissions sent
-
Your build clock starts
Septic or general building permit issued
Week 1 begins the day the county issues your permit. Every date below counts from here.
-
Weeks 1–4
Site work & foundation
- Clearing, grading and erosion control
- Footings and foundation walls or slab
- Underground plumbing and sleeves
- Footing and foundation inspections
- Termite treatment and vapor barrier (if applicable)
- Draw request from lender (construction loan)
-
Buyer walk-through
Lot & foundation walk
Walk your lot and foundation with us to see where your home sits.
-
Weeks 5–8
Framing & rough-ins begin
- Floors, walls and roof framed
- Roof dried in; windows and exterior doors set
- House wrap and sheathing complete
- Rough plumbing, HVAC and electrical begin
- Framing inspection
- Window flashing and roof dry-in verified
-
Buyer walk-through
Framing & electrical walk
Before drywall, confirm outlet and switch locations, hose bibs and gas stubs.
-
Weeks 9–12
Rough-ins complete, before drywall
- Rough electrical, plumbing and HVAC completed
- Fireplace unit set (if included)
- Exterior cladding starts
- Rough inspections: mechanical, plumbing and electrical
- Insulation inspection scheduled
- Low-voltage and security prewires verified
-
Weeks 13–16
Insulation & interior finishes start
- Insulation installed and inspected
- Drywall hung and finished
- Interior trim and doors set
- Cabinets installed; tile prep begins
- Exterior finishes and driveway progress
- Drywall finish approved by builder
- Countertop templates scheduled
- Appraisal usually ordered now that interiors are visible
-
Buyer walk-through
Drywall walk
Verify your cabinet types and locations.
-
Weeks 17–21
Fit-out, punch list & closing prep
- Hard-surface flooring, tile and counters installed
- Plumbing and lighting fixtures set
- Appliances delivered and set after flooring
- Final paint, mirrors, shower glass and hardware
- Landscaping and final clean
- Final building inspections and certificate of occupancy
- Lender appraisal received and final conditions cleared
-
Buyer walk-through
Blue tape walk & homeowner orientation
Review your home's systems, maintenance and warranties, and make a short punch list together.
-
Buyer walk-through
Final walk-through
Confirm the punch list is complete before closing.
-
Week 22
Closing. Welcome home.